As a result of the local market’s high demand for telecommunication space, TrizecHahn Office Properties Ltd. chose to convert its 300,000 s.f.  building at 151 Front Street West to a Class “A” telecommunications hotel carrier. To support tenants’ installation of equipment, such as generators, cooling towers and fuel storage tanks, Jones Lang LaSalle was engaged to manage the base building’s electrical and mechanical systems upgrade process. The project included an aggressive two-phase schedule and a $4 million budget.

A best-in-class project team was assembled to address the challenging task of installing major mechanical and electrical equipment not programmed in the design of the original building. We constructed a riser shaft with diversification, major electrical supply and major HVAC supply to bring all of the systems in the building up to the tenants’ required specifications.
 
Phase I was completed on time and within budget by July 2000.  Phase II was on schedule and completed in March 2001. As a result of the successful upgrade, the landlord was able to maximize income by providing specialized services to each of tenants.

All case studies

 

 

Brockville General Hospital - Bringing new life to BGH/canada/en-ca/case-studies/3/brockville-general-hospital-bringing-new-life-to-bghBrockville General Hospital - Bringing new life to BGHThe Brockville General Hospital (BGH) had commenced construction of a $28 million, 70,000 s.f. expansion project which included new Emergency, Recovery, Radiology, ICU, OR, Sterilization and Maternity Departments.
Olympic Stadium - Soaring to new heights/canada/en-ca/case-studies/4/olympic-stadium-soaring-to-new-heightsOlympic Stadium - Soaring to new heightsThe Project and Development Management service group of Jones Lang LaSalle in Montreal was awarded the redevelopment project of the Olympic Stadium Tower.
Crofton Moore - A success from start to finish/canada/en-ca/case-studies/5/crofton-moore-a-success-from-start-to-finishCrofton Moore - A success from start to finishThe development project consisted of tearing down an old food warehousing plant and converting vacant land into a 120,000 s.f. retail power centre, which consists of 3 single tenant buildings, 3 multi tenant buildings and all related site services.